@ 2002-06-21 00:13 Josh Berkus <josh@agliodbs.com>
  2002-06-21 05:32 ` Re: SQL Challenge:  Skip Weekends Joe Conway <mail@joeconway.com>
  2002-06-21 17:46 ` Re: SQL Challenge:  Skip Weekends Jean-Luc Lachance <jllachan@nsd.ca>
  0 siblings, 2 replies; 5+ messages in thread

From: Josh Berkus @ 2002-06-21 00:13 UTC (permalink / raw)
  To: pgsql-sql

Folks,

Hey, I need to write a date calculation function that calculates the date 
after a number of *workdays* from a specific date.   I pretty much have the 
"skip holidays" part nailed down, but I don't have a really good way to skip 
all weekends in the caluclation.  Here's the ideas I've come up with:

Idea #1: Use a reference table
1. Using a script, generate a table of all weekends from 2000 to 2050.
2. Increase the interval by the number of weekends that fall in the relevant 
period.

Idea #2:  Some sort of calculation using 5/7 of the interval, adjusted 
according to the day of the week of our starting date.  My head hurts trying 
to figure this one out.

-- 
-Josh Berkus






^ permalink  raw  reply  [nested|flat] 5+ messages in thread

* Re: SQL Challenge:  Skip Weekends
  2002-06-21 00:13 SQL Challenge:  Skip Weekends Josh Berkus <josh@agliodbs.com>
@ 2002-06-21 05:32 ` Joe Conway <mail@joeconway.com>
  2002-06-21 19:31   ` Re: SQL Challenge:  Skip Weekends Josh Berkus <josh@agliodbs.com>
  1 sibling, 1 reply; 5+ messages in thread

From: Joe Conway @ 2002-06-21 05:32 UTC (permalink / raw)
  To: josh@agliodbs.com; +Cc: pgsql-sql

Josh Berkus wrote:
 > Folks,
 >
 > Hey, I need to write a date calculation function that calculates the
 > date after a number of *workdays* from a specific date.   I pretty
 > much have the "skip holidays" part nailed down, but I don't have a
 > really good way to skip all weekends in the caluclation.  Here's the
 > ideas I've come up with:

How about this (a bit ugly, but I think it does what you want -- minus 
the holidays, which you said you already have figured out):

create or replace function
   get_future_work_day(timestamp, int)
   returns timestamp as '
select
   case when extract(dow from future_work_date) = 6
             then future_work_date + ''2 days''
        when extract(dow from future_work_date) = 0
             then future_work_date + ''1 day''
        else
             future_work_date
   end
from
   (
      select $1
             + (($2 / 5)::text || '' weeks'')
             + (($2 % 5)::text || '' days'')
             as future_work_date
   ) as t1
' language sql;
CREATE
testslv=# select get_future_work_day('2002-06-20',27);
   get_future_work_day
------------------------
  2002-07-29 00:00:00-07
(1 row)

HTH,
Joe





^ permalink  raw  reply  [nested|flat] 5+ messages in thread

* Re: SQL Challenge:  Skip Weekends
  2002-06-21 00:13 SQL Challenge:  Skip Weekends Josh Berkus <josh@agliodbs.com>
  2002-06-21 05:32 ` Re: SQL Challenge:  Skip Weekends Joe Conway <mail@joeconway.com>
@ 2002-06-21 19:31   ` Josh Berkus <josh@agliodbs.com>
  0 siblings, 0 replies; 5+ messages in thread

From: Josh Berkus @ 2002-06-21 19:31 UTC (permalink / raw)
  To: Joe Conway <mail@joeconway.com>; josh@agliodbs.com; +Cc: pgsql-sql

Joe,

> How about this (a bit ugly, but I think it does what you want --
> minus the holidays, which you said you already have figured out):
> 
> create or replace function
>   get_future_work_day(timestamp, int)

Thank you.  Once again, you come to the rescue when I'm stuck.  I'll
try your solution and Jean-Luc's, and see which works better/faster.
  And report back.

-Josh Berkus



^ permalink  raw  reply  [nested|flat] 5+ messages in thread

* Re: SQL Challenge:  Skip Weekends
  2002-06-21 00:13 SQL Challenge:  Skip Weekends Josh Berkus <josh@agliodbs.com>
@ 2002-06-21 17:46 ` Jean-Luc Lachance <jllachan@nsd.ca>
  2002-06-21 19:29   ` Re: SQL Challenge:  Skip Weekends Josh Berkus <josh@agliodbs.com>
  1 sibling, 1 reply; 5+ messages in thread

From: Jean-Luc Lachance @ 2002-06-21 17:46 UTC (permalink / raw)
  To: josh@agliodbs.com; +Cc: pgsql-sql

here is the algorithm:

date := now - day_of_the_week
interval := interval + day_of_the_week
date := date + int( interval/5)x7 + ( interval mod 5)


Josh Berkus wrote:
> 
> Folks,
> 
> Hey, I need to write a date calculation function that calculates the date
> after a number of *workdays* from a specific date.   I pretty much have the
> "skip holidays" part nailed down, but I don't have a really good way to skip
> all weekends in the caluclation.  Here's the ideas I've come up with:
> 
> Idea #1: Use a reference table
> 1. Using a script, generate a table of all weekends from 2000 to 2050.
> 2. Increase the interval by the number of weekends that fall in the relevant
> period.
> 
> Idea #2:  Some sort of calculation using 5/7 of the interval, adjusted
> according to the day of the week of our starting date.  My head hurts trying
> to figure this one out.
> 
> --
> -Josh Berkus
> 
> ---------------------------(end of broadcast)---------------------------
> TIP 4: Don't 'kill -9' the postmaster



^ permalink  raw  reply  [nested|flat] 5+ messages in thread

* Re: SQL Challenge:  Skip Weekends
  2002-06-21 00:13 SQL Challenge:  Skip Weekends Josh Berkus <josh@agliodbs.com>
  2002-06-21 17:46 ` Re: SQL Challenge:  Skip Weekends Jean-Luc Lachance <jllachan@nsd.ca>
@ 2002-06-21 19:29   ` Josh Berkus <josh@agliodbs.com>
  0 siblings, 0 replies; 5+ messages in thread

From: Josh Berkus @ 2002-06-21 19:29 UTC (permalink / raw)
  To: Jean-Luc Lachance <jllachan@nsd.ca>; josh@agliodbs.com; +Cc: pgsql-sql

Jean-Luc,

> date := now - day_of_the_week
> interval := interval + day_of_the_week
> date := date + int( interval/5)x7 + ( interval mod 5)

Merci, merci, merci!

-Josh



^ permalink  raw  reply  [nested|flat] 5+ messages in thread


end of thread, other threads:[~2002-06-21 19:31 UTC | newest]

Thread overview: 5+ messages (download: mbox mbox.gz follow: Atom feed)
-- links below jump to the message on this page --
2002-06-21 00:13 SQL Challenge:  Skip Weekends Josh Berkus <josh@agliodbs.com>
2002-06-21 05:32 ` Joe Conway <mail@joeconway.com>
2002-06-21 19:31   ` Josh Berkus <josh@agliodbs.com>
2002-06-21 17:46 ` Jean-Luc Lachance <jllachan@nsd.ca>
2002-06-21 19:29   ` Josh Berkus <josh@agliodbs.com>

This inbox is served by DDX for PostgreSQL; see mirroring instructions
for how to clone and mirror all data and code used for this inbox