From: Murtuza Zabuawala <[email protected]>
To: Dave Page <[email protected]>
Cc: pgadmin-hackers <[email protected]>
Subject: Re: [pgAdmin4][RM#3073] Allow user to schedule without End date from UI
Date: Tue, 27 Feb 2018 17:29:53 +0530
Message-ID: <CAKKotZSbDqjKKNaprnXM7eEW3wR1ffbDbmmh2B-xqtybUVv_Bw@mail.gmail.com> (raw)
In-Reply-To: <CA+OCxox8yPw33SHwvTmbtDJcgCjYx2nMZf3dFFk6hk0A6=HX3w@mail.gmail.com>
References: <CAKKotZR-a320X7Jq30Nf+wWNk13z_TV-DLPsZNdaZHw9wj5oiQ@mail.gmail.com>
	<CA+OCxoy7sOE1xUZWtdyi2UJjJucQCTjcJy=ep21KqsbXEi-Bsw@mail.gmail.com>
	<CAKKotZQ_QLJ+pgz0Q8Tjg3-oOezG7OTUXDSgg_SYXm2pX4itgQ@mail.gmail.com>
	<CA+OCxox8yPw33SHwvTmbtDJcgCjYx2nMZf3dFFk6hk0A6=HX3w@mail.gmail.com>

Hi Dave,

Could you please send screenshot?

--
Regards,
Murtuza Zabuawala
EnterpriseDB: http://www.enterprisedb.com
The Enterprise PostgreSQL Company


On Tue, Feb 27, 2018 at 5:24 PM, Dave Page <[email protected]> wrote:

> Hi
>
> Still not quite right - see the attached screenshot which is the result of
> simply viewing the properties of an existing job. Note that the start time
> is shown in the grid but not the subnode control.
>
> Thanks.
>
> On Tue, Feb 27, 2018 at 8:26 AM, Murtuza Zabuawala <murtuza.zabuawala@
> enterprisedb.com> wrote:
>
>> Hi Dave,
>>
>> As validation related patch was committed with RM#3148 [ Sorry about that
>> I forgot to checkout :) ]
>> PFA patch to fix the issues you mentioned, I have also removed extra
>> error message from sub node collection control and made it optional via
>> flag.
>>
>>
>>
>> --
>> Regards,
>> Murtuza Zabuawala
>> EnterpriseDB: http://www.enterprisedb.com
>> The Enterprise PostgreSQL Company
>>
>>
>> On Mon, Feb 26, 2018 at 10:14 PM, Dave Page <[email protected]> wrote:
>>
>>> Hi
>>>
>>> On Mon, Feb 26, 2018 at 2:46 PM, Murtuza Zabuawala <
>>> [email protected]> wrote:
>>>
>>>> Hi,
>>>>
>>>> PFA patch to fix the issue where user was not able to create pgAgent
>>>> job from UI without entering End date in schedule section.
>>>>
>>>
>>>  Whilst this does resolve the validation issue, there are still a couple
>>> of other related problems, as can be seen in the attached screenshots:
>>>
>>> - The Start date/time in the subnode control doesn't seem to be properly
>>> synchronised with the value in the grid.
>>>
>>> - If you leave the End date/time blank (but maybe click into it first),
>>> the grid will show "Invalid date".
>>>
>>> It's possible there are other oddities as well - please check carefully
>>> for anything else.
>>>
>>> Thanks.
>>>
>>> --
>>> Dave Page
>>> Blog: http://pgsnake.blogspot.com
>>> Twitter: @pgsnake
>>>
>>> EnterpriseDB UK: http://www.enterprisedb.com
>>> The Enterprise PostgreSQL Company
>>>
>>
>>
>
>
> --
> Dave Page
> Blog: http://pgsnake.blogspot.com
> Twitter: @pgsnake
>
> EnterpriseDB UK: http://www.enterprisedb.com
> The Enterprise PostgreSQL Company
>


view thread (14+ messages)  latest in thread

reply

Reply instructions:

You may reply publicly to this message via plain-text email
using any one of the following methods:

* Reply to all the recipients using the --to and --cc options:
  reply via email

  To: [email protected]
  Cc: [email protected], [email protected]
  Subject: Re: [pgAdmin4][RM#3073] Allow user to schedule without End date from UI
  In-Reply-To: <CAKKotZSbDqjKKNaprnXM7eEW3wR1ffbDbmmh2B-xqtybUVv_Bw@mail.gmail.com>

* Save the following mbox file, import it into your mail client,
  and reply-to-all from there: mbox

This inbox is served by agora; see mirroring instructions
for how to clone and mirror all data and code used for this inbox