help / color / mirror / Atom feedFrom: Murtuza Zabuawala <[email protected]>
To: Dave Page <[email protected]>
Cc: pgadmin-hackers <[email protected]>
Subject: Re: [pgAdmin4][RM#3073] Allow user to schedule without End date from UI
Date: Tue, 27 Feb 2018 17:33:55 +0530
Message-ID: <CAKKotZTA_zDhuarKGhqYVaGf0u7bb72uvaJoWkOdRPWKmDqPyg@mail.gmail.com> (raw)
In-Reply-To: <CA+OCxoxWZUZX1KAXr+_xyagF8Zai21C7YAC_Sfb5ZJwm-ywMLA@mail.gmail.com>
References: <CAKKotZR-a320X7Jq30Nf+wWNk13z_TV-DLPsZNdaZHw9wj5oiQ@mail.gmail.com>
<CA+OCxoy7sOE1xUZWtdyi2UJjJucQCTjcJy=ep21KqsbXEi-Bsw@mail.gmail.com>
<CAKKotZQ_QLJ+pgz0Q8Tjg3-oOezG7OTUXDSgg_SYXm2pX4itgQ@mail.gmail.com>
<CA+OCxox8yPw33SHwvTmbtDJcgCjYx2nMZf3dFFk6hk0A6=HX3w@mail.gmail.com>
<CAKKotZSbDqjKKNaprnXM7eEW3wR1ffbDbmmh2B-xqtybUVv_Bw@mail.gmail.com>
<CA+OCxoxWZUZX1KAXr+_xyagF8Zai21C7YAC_Sfb5ZJwm-ywMLA@mail.gmail.com>
I'm not able to re-produce the issue, Could you hard refresh and try again?
If possible could you please provide exact steps?
--
Regards,
Murtuza Zabuawala
EnterpriseDB: http://www.enterprisedb.com
The Enterprise PostgreSQL Company
On Tue, Feb 27, 2018 at 5:30 PM, Dave Page <[email protected]> wrote:
> Sorry - here it is.
>
> On Tue, Feb 27, 2018 at 11:59 AM, Murtuza Zabuawala <murtuza.zabuawala@
> enterprisedb.com> wrote:
>
>> Hi Dave,
>>
>> Could you please send screenshot?
>>
>> --
>> Regards,
>> Murtuza Zabuawala
>> EnterpriseDB: http://www.enterprisedb.com
>> The Enterprise PostgreSQL Company
>>
>>
>> On Tue, Feb 27, 2018 at 5:24 PM, Dave Page <[email protected]> wrote:
>>
>>> Hi
>>>
>>> Still not quite right - see the attached screenshot which is the result
>>> of simply viewing the properties of an existing job. Note that the start
>>> time is shown in the grid but not the subnode control.
>>>
>>> Thanks.
>>>
>>> On Tue, Feb 27, 2018 at 8:26 AM, Murtuza Zabuawala <
>>> [email protected]> wrote:
>>>
>>>> Hi Dave,
>>>>
>>>> As validation related patch was committed with RM#3148 [ Sorry about
>>>> that I forgot to checkout :) ]
>>>> PFA patch to fix the issues you mentioned, I have also removed extra
>>>> error message from sub node collection control and made it optional via
>>>> flag.
>>>>
>>>>
>>>>
>>>> --
>>>> Regards,
>>>> Murtuza Zabuawala
>>>> EnterpriseDB: http://www.enterprisedb.com
>>>> The Enterprise PostgreSQL Company
>>>>
>>>>
>>>> On Mon, Feb 26, 2018 at 10:14 PM, Dave Page <[email protected]> wrote:
>>>>
>>>>> Hi
>>>>>
>>>>> On Mon, Feb 26, 2018 at 2:46 PM, Murtuza Zabuawala <
>>>>> [email protected]> wrote:
>>>>>
>>>>>> Hi,
>>>>>>
>>>>>> PFA patch to fix the issue where user was not able to create pgAgent
>>>>>> job from UI without entering End date in schedule section.
>>>>>>
>>>>>
>>>>> Whilst this does resolve the validation issue, there are still a
>>>>> couple of other related problems, as can be seen in the attached
>>>>> screenshots:
>>>>>
>>>>> - The Start date/time in the subnode control doesn't seem to be
>>>>> properly synchronised with the value in the grid.
>>>>>
>>>>> - If you leave the End date/time blank (but maybe click into it
>>>>> first), the grid will show "Invalid date".
>>>>>
>>>>> It's possible there are other oddities as well - please check
>>>>> carefully for anything else.
>>>>>
>>>>> Thanks.
>>>>>
>>>>> --
>>>>> Dave Page
>>>>> Blog: http://pgsnake.blogspot.com
>>>>> Twitter: @pgsnake
>>>>>
>>>>> EnterpriseDB UK: http://www.enterprisedb.com
>>>>> The Enterprise PostgreSQL Company
>>>>>
>>>>
>>>>
>>>
>>>
>>> --
>>> Dave Page
>>> Blog: http://pgsnake.blogspot.com
>>> Twitter: @pgsnake
>>>
>>> EnterpriseDB UK: http://www.enterprisedb.com
>>> The Enterprise PostgreSQL Company
>>>
>>
>>
>
>
> --
> Dave Page
> Blog: http://pgsnake.blogspot.com
> Twitter: @pgsnake
>
> EnterpriseDB UK: http://www.enterprisedb.com
> The Enterprise PostgreSQL Company
>
view thread (14+ messages) latest in thread
reply
Reply instructions:
You may reply publicly to this message via plain-text email
using any one of the following methods:
* Reply to all the recipients using the --to and --cc options:
reply via email
To: [email protected]
Cc: [email protected], [email protected]
Subject: Re: [pgAdmin4][RM#3073] Allow user to schedule without End date from UI
In-Reply-To: <CAKKotZTA_zDhuarKGhqYVaGf0u7bb72uvaJoWkOdRPWKmDqPyg@mail.gmail.com>
* Save the following mbox file, import it into your mail client,
and reply-to-all from there: mbox
This inbox is served by agora; see mirroring instructions
for how to clone and mirror all data and code used for this inbox